FEDERAL COURT OF AUSTRALIA

 

Clough Engineering Ltd v Oil & Natural Gas Corporation Ltd [2007] FCA 881  



INJUNCTION – interim interlocutory injunction – whether serious issues to be tried – whether applicant contractor may enjoin respondent principal from taking further steps to demand or obtain payment under performance guarantees issued by respondent banks – whether applicant contractor guilty of unconscionable conduct in contravention of Trade Practices Act 1974 (Cth) s 51AA.   


PRACTICE AND PROCEDURE – leave to serve proceeding in India – Federal Court Rules O 8 – whether proceeding of kind(s) mentioned in O 8 r 2 – whether prima facie case of contravention of s 51AA if the Trade Practices Act 1974 (Cth) by calling on performance guarantees by respondent banks when no contractual entitlement to do so.  


Trade Practices Act 1974 (Cth), ss 2, 4(1), 51AA, 80(1), 82, 86(1), 87

Judiciary Act 1903 (Cth), s 39B(1A)(c)



ACCC v Samton Holdings Pty Ltd (2002) 117 FCR 301

ACCC v CG Berbatis Holdings Pty Ltd (2003) 214 CLR 51

Akai Pty Ltd v People Insurance Co Ltd (1996) 188 CLR 418

Australian Broadcasting Corp v O'Neill (2006) 229 ALR 457,

Australian Competition and Consumer Commission v Samton Holdings Pty Ltd (2002) 117 FCR 301

Australian Winch and Haulage Company Pty Ltd (admin appt) v Walter Construction Group Ltd [2002] FCA 1181

Bolivinter Oil SA v Chase Manhattan Bank NA [1984] 1 WLR 392

Boral Formwork v Action Makers (2003) ATPR 41-953

Bray v F Hoffmann-La Roche Ltd (2003) 130 FCR 317

Burgundy Royale Investments v Westpac Banking Corporation (1987) 18 FCR 212

Clark Equipment Australia Ltd v Covcat Pty Ltd (1987) 71 ALR 367

Commonwealth Bank of Australia v White [1999] 2 VR 681

Darlington Futures Ltd v Delco Australia Pty Ltd (1986) 161 CLR 500

Dunlop Rubber Co Ltd v Dunlop [1921] 1 AC 367

Edward Owen Engineering Ltd v Barclays Bank International Ltd [1978] 1 QB 159

Entores Ltd v Miles Far East Corporation [1955] 2 QB 327

Esal (Commodities) Ltd v Oriental Credit Ltd [1985] 2 Lloyd's Rep 546

Eurogold Ltd v Oxus Holdings (Malta) Ltd [2007] FCA 811

Fletcher Construction Australia Ltd v Varnsdorf Pty Ltd [1998] 3 VR 812

Foran v Wight (1989) 168 CLR 385

Henjo Investments Pty Ltd v Collins Marrickville Pty Ltd (No 1) (1988) 39 FCR 546

Hi-Fert Pty Ltd v Kukiang Maritime Carrier Inc (1998) 90 FCR 1

Hortico (Aust) Pty Ltd v Energy Equipment Co (Aust) Pty Ltd[1985] 1 NSWLR 545

Houghton v Arms (2006) 231 ALR 534

Hume Computers Pty Ltd v Exact International BV[2006] FCA 1440

IE Contractors Ltd v Lloyds Bank plc [1990] 2 Lloyd's Rep 496

IOOF Australia Trustees (NSW) Ltd v Tantipech (1998) 156 ALR 470

Leigh-Mardon Pty Ltd v PRC Inc (1993) 44 FCR 88

Mackay v Dick (1881) 6 App Cas 251

Merpro Montassa Ltd v Conoco Specialty Products Inc (1991) 28 FCR 387

Neilson v Overseas Projects Corp of Victoria Ltd (2005) 223 CLR 331

Newcombe v Newcombe (1934) 34 SR (NSW) 446

Olex Focas Pty Ltd v Skodaexport Co Ltd [1998] 3 VR 380

Peak Construction (Liverpool) Ltd v McKinney Foundations Ltd (1970)1 BLR 114

Pierce Bell Sales Pty Ltd v Frazer (1973) 130 CLR 575

Pearson Bridge (NSW) Pty Ltd v State Rail Authority of New South Wales(1982) 1 Australian Construction LR 81

Permanent Trustee Co (Canberra) Ltd v Permanent Trustee Co of New South Wales Ltd (1969) 14 FLR 246

Potton Holmes Ltd v Coleman Contractors Ltd (1984) 28 BLR 19

QS Retail Pty Ltd v Kingvest Pty Ltd [2006] VSC 455

Quinlan v Safe International Forsakrings AB [2005] FCA 1362

Rejan Constructions Pty Ltd v Manningham Medical Centre Pty Ltd [2002] VSC 579

Roberts v Bury Improvement Commissioners (1870) LR 5 CP 310

Selvas Pty Ltd v Hansen & Yuncken (SA) Pty Ltd (1987) 6 Australian Construction LR 36

Solo Industries UK Ltd v Canara Bank [2001] 1 WLR 1800

Sydbank Soenderjylland A/S v Bannerton Holdings Pty(1996) 68 FCR 539

Tana v Baxter (1986) 160 CLR 572

Tanwar v Enterprises Pty Ltd v Cauchi (2003) 217 CLR 315

Themehelp Ltd v West [1996] QB 84

Traxon Industries Pty Ltd v Emerson Electric Co (2006) 230 ALR 297

Turner Corporation Ltd v Co-Ordinated Industries Pty Ltd (1995) 12 BCL 33

Voth v Manildra Flour Mills Pty Ltd (1990) 171 CLR 538

Walker v ANZ Banking Group Ltd (No 2) (2001) 39 ACSR 557

Western Australia v Vetter Trittler (1991) 30 FCR 102

Wood Hall Ltd v Pipeline Authority (1979) 141 CLR 443


CLOUGH ENGINEERING LIMITED v OIL AND NATURAL GAS CORPORATION LIMITED, COMMONWEALTH BANK OF AUSTRALIA (ACN 123 123 124), HSBC BANK AUSTRALIA LIMITED (ACN 006 434 162) AND BNP PARIBAS (ABN 23 000 000 117)

WAD117 OF 2007

 

 

GILMOUR J

7 JUNE 2007

PERTH




IN THE FEDERAL COURT OF AUSTRALIA

 

WESTERN AUSTRALIA DISTRICT REGISTRY

WAD117 OF 2007

 

BETWEEN:

CLOUGH ENGINEERING LIMITED

Applicant

 

AND:

OIL AND NATURAL GAS CORPORATION LIMITED

First Respondent

 

COMMONWEALTH BANK OF AUSTRALIA

(ACN 123 123 124)

Second Respondent

 

HSBC BANK AUSTRALIA LIMITED (ACN 006 434 162)

Third Respondent

 

BNP PARIBAS (ABN 23 000 000 117)

Fourth Respondent

 

 

JUDGE:

GILMOUR J

DATE OF ORDER:

7 JUNE 2007

WHERE MADE:

PERTH

 

THE COURT ORDERS THAT:

 

1.                  The Applicant have leave to amend its Application in terms of the minute of Amended Application.

2.                  Leave is granted to serve the Amended Application outside the Commonwealth of Australia, namely, in India, on the First Respondent at Jeevan Bharati, Tower-II, 124 Indira Chowk, New Delhi – 110 001, with the service of the Amended Application to be accompanied by a copy of the Affidavits Kulasegaram Siritharan sworn on 25 May 2007, Affidavit of Malcolm Rutter 5 June 2007, Affidavits of Jae-Ho Choe sworn on 5 June 2007, Affidavit of Richard Francis Simons sworn on 28 May 2007, and any further affidavits filed in support of the Amended Application.  

3.                  Upon the Applicant providing an undertaking as to damages, the First Respondent be restrained and an injunction is hereby granted, until 4.15 pm on 12 June 2007 or further order, restrained the First Respondent from:

(a)                taking any further step to demand or to obtain payment; or

(b)               renewing or claiming to renew a demand for payment,

from any one or more of the Second, Third or Fourth Defendant under the performance guarantees granted by the Second, Third and Fourth Respondents dated 14 January, 19 January and 13 January 2005 respectively.

4.                  There be liberty to apply.

5.                  These proceedings be adjourned until 10.15 am 12 June 2007.

6.                  Costs be reserved.


Note:    Settlement and entry of orders is dealt with in Order 36 of the Federal Court Rules.


IN THE FEDERAL COURT OF AUSTRALIA

 

WESTERN AUSTRALIA DISTRICT REGISTRY

WAD117 OF 2007

 

BETWEEN:

CLOUGH ENGINEERING LIMITED

Applicant

 

AND:

OIL AND NATURAL GAS CORPORATION LIMITED

First Respondent

 

COMMONWEALTH BANK OF AUSTRALIA

(ACN 123 123 124)

Second Respondent

 

HSBC BANK AUSTRALIA LIMITED

(ACN 006 434 162)

Third Respondent

 

BNP PARIBAS (ABN 23 000 000 117)

Fourth Respondent

 

 

JUDGE:

GILMOUR J

DATE:

7 JUNE 2007

PLACE:

PERTH

 

REASONS FOR JUDGMENT

1                     The applicant, Clough Engineering Limited (“Clough”) seeks leave of the Court pursuant to Order 8 of the Federal Court Rules to serve its application as amended on 6 June 2007 out of the jurisdiction, in India, on the first respondent Oil and Natural Gas Corporation Limited (“ONGC”).  It also moves for orders to restrain ONGC from taking further steps to demand or obtain payment or renewing or claiming to renew such demand in respect to certain performance guarantees granted by the three respondent banks to ONGC. 

2                     The application is supported by affidavits sworn by Jae-Ho Choe of 5 June 2007; Kulasegaram Sirithiran of 25 May 2007 and Malcolm Rutter of 5 June 2007.  It is from these affidavits that the factual matters to which I will refer have been sourced.

3                     In the substantive application, in addition to permanent injunctive relief, Clough seeks declarations concerning a construction contract entered into between it and ONGC.  The contract is an engineering, procurement, installation and commissioning contract for the development of certain oil and gas fields in the Krishna Godavari basin off the coast of the state of Andhra Pradesh in India.  The declaratory relief sought is that upon the proper construction the contract entered into between Clough and ONGC on 30 November 1994 as recorded in an instrument dated 6 January 2005, and in the events which happened, ONGC by demanding and threatening to make a demand on the performance guarantees granted by the second, third and fourth respondents has engaged in, or proposes to engage in, unconscionable conduct in contravention of s 51AA of the Trade Practices Act 1976 (Cth) (“the Act”). 

4                     It also seeks, on the same footing, an interim interlocutory injunction to restrain ONGC broadly in the terms to which I have referred above in respect to the performance guarantees granted by each of the respondent banks dated 14 January, 19 January and 13 January 2005 respectively.  Those performance guarantees were provided pursuant to the terms of the contract between Clough and ONGC. 

5                     Clough also claims, relevantly, damages pursuant to s 82 of the Act and/or other orders pursuant to s 87 of the Act arising from ONGC’s alleged contravention of s 51AA of the Act. 

6                     On 5 June 2007 I made interim interlocutory injunctive orders restraining each of the three respondent banks from making payment to ONGC under their respective performance guarantees.

7                     In granting those orders I concluded that there were serious questions to be tried whether ONGC was entitled under the contract to call on the Banks to make payment under the performance guarantees.  The reasons here should be read in conjunction with the reasons I gave ex tempore for making those orders.  I am indebted to counsel for the applicant for the considerable assistance provided to the Court in their very detailed written submissions, in respect of what is a relatively complex matter.  I have drawn heavily upon these in compiling these reasons. 

BACKGROUND

8                     In August 2004, Clough tendered for an engineering, procurement, installation and commissioning contract with ONGC for the development of certain oil/ gas fields in the Krishna Godavari basin off the coast of the state of Andhra Pradesh, India. 

9                     By facsimile of 30 November 2004 from ONGC to Clough, received by Clough in Perth, ONGC notified Clough that it had been successful in being awarded the contract for execution of certain works. The facsimile stated that ‘This Notification of Award shall constitute binding Contract between CLOUGH and ONGC, and shall be subject to all terms and conditions of the Bidding Documents and other documents mentioned in Para 1.0 above.’ On receipt of the facsimile, ONGC and Clough had entered into a binding agreement. The parties had agreed to be bound immediately even though there would be a more formal agreement subsequently executed. 

10                  By para 8.0 of the facsimile, Clough was required to sign a formal contract with ONGC. On 6 January 2005, a formal agreement was made between ONGC and Clough under which it was recited that ONGC had awarded to Clough the contract at a negotiated lump sum of US$215,351,156.33 by its facsimile of 30 November 2004 on the terms and conditions as agreed to by the parties as of the date of the facsimile and as outlined in the formal agreement. 

11                  The formal agreement made on 6 January 2005 incorporated annexure A (General Conditions of Contract), annexure B (bidding documents, including the facsimile of 30 November 2004), annexure C (Contract price schedule and Rental Rate Schedule), annexure D (Construction schedule/ Project Key Dates), annexure E (Project Instructions) and annexure F (Milestone payment formula giving break-up of the negotiated lump sum prices). 

12                  The overall project to which the contract relates involves three main elements, namely the construction of (i) an onshore gas processing plant, (ii) a shallow water field and (iii) a deep water field.  

13                  Clough’s scope of work under the contract was essentially to:

(a)                design and build an onshore gas processing plant;

(b)               design, supply and install one wellhead platform for the shallow water field;

(c)                design and modify an existing wellhead platform in the shallow water field;

(d)               design, supply and install a sub sea production system in the deep water field;

(e)                supply and lay the pipeline network; and

(f)                 undertake commissioning.

14                  The overall project also included certain drilling and well-completion work, both in the shallow water field and in the deep water field. This work was not part of Clough’s scope of work under the contract. ONGC was to carry out the drilling and well-completion work itself.  This work had to be carried out before Clough could complete its offshore scope of work.  ONGC has not effected well-completion.  That has delayed the project’s completion. This is because the offshore work, namely the shallow water work and the deep water work, was contractually agreed to be done together with one mobilisation and de-mobilisation of the required spread, in the same campaign.  The deep water work cannot be completed because it is directly dependent on well-completion.  Moreover, the onshore work cannot be completed and the onshore plant commissioned, until there is a flow of hydrocarbons from the deep water wells. 95% of the hydrocarbons for the plant was to come from the deep water wells.  

15                  The contract contained certain provisions for liquidated damages, as a genuine pre-estimate of damage rather than a penalty, to apply if completion was delayed beyond 15 April 2006. 

16                  As a result of delay caused by ONGC, on Clough’s request for an agreement for extension, the original contract completion date of 15 April 2006 was extended until 13 April 2007.  Because of ONGC’s further delays (in effecting well-completion), the work cannot be completed by 13 April 2007.  Clough sought further agreement for extension, and ONGC has recently said that it ‘provisionally’ extended the completion date to 30 April 2008.  There has been no agreement between the parties concerning the potential application of liquidated damages to any delays occurring after 13 April 2007 or 30 April 2008. 

17                  Clough has made various claims on ONGC, including for delay costs, in the total sum of about US$125m.  ONGC has rejected these claims.  

18                  The parties agreed in or about July 2006 to refer the dispute to an outside expert committee (OEC) for non‑binding adjudication. That process has itself been delayed. 

19                  Under the contract, progress payments are to be made by ONGC if the payment procedure in the contract is followed. Despite the procedure having been followed, some US$7 million of invoiced and undisputed amounts have not been paid by ONGC to Clough, in breach of the obligation to do so under cl 3.2.4.  

20                  On 11 December 2006, ONGC asked Clough to submit a proposal by which Clough would install the shallow water wellhead platform on its own, separately from the other off-shore work. The contract does not provide for this work to be carried out on its own. Under the original agreed contractual program, which is annexure D of the formal agreement, Clough was to commission all platforms (deep and shallow water) in the same campaign. The work to commission the shallow water wellhead platform alone will involve mobilising much of the same marine spread as would be required to complete both the shallow water and deep water installations as originally contemplated by Clough’s program.

21                  On 25 January 2006, Clough submitted a price to commission the shallow water field only.  On 8 February 2006, ONGC rejected Clough’s proposal but did not direct Clough to carry out that work. ONGC instead asserted that Clough was required to decide the best option to complete the shallow water work.  Although the issue had been raised by Clough, including at the meeting on 11 December 2006, ONGC refused to recognise that the contract provided for the shallow water work and the deep water work to be done together.  ONGC, therefore, did not agree to pay Clough the extra amounts needed to effect the shallow water work alone.  Nor did ONGC recognise that the requirement to do the shallow water work separately was not contemplated by the contract.  

22                  By letters of 29 January 2007 and 8 February 2007, ONGC threatened to call on the performance guarantees. ONGC has also threatened to require payment of liquidated damages.  Clough contends that ONGC cannot lawfully serve a notice of demand under the performance guarantees or obtain liquidated damages.  Because attempted commercial negotiations in the months of February, March, April and May 2007 between the parties has not broken the impasse between them, Clough feared that the performance guarantees might be called, without notice to Clough.  It was for this reason that the application for injunctive relief was brought ex parte.  As it transpired ONGC in fact purported to call on the performance guarantees shortly before this matter came before the Court.

23                  There remain allegations by ONGC, that Clough is in breach of contract, and allegations by Clough, that ONGC is in breach of contract.  Each party denies the other’s allegations and for its part, Clough also contends that no damage arises even if there were breaches.  The principal claims by ONGC appear to be:

(a)                Clough has not delivered, as is the fact, 3 “Christmas Trees”, for which Clough accepts it has largely been paid; 

(b)               Clough has failed to undertake, as is the fact, certain shallow water works and on-shore works separately from the off-shore works.

24                  There has been no determination of these disputes by arbitration or otherwise.

THE REQUIREMENTS FOR LEAVE

25                  Leave is requiredto serve ONGC outside Australia, in India.  Under FCR O 8, r 3(2), the Court may give leave to serve ONGC in India in accordance with the laws of India, if the Court has jurisdiction in the proceeding; the proceeding is of a kind mentioned in rule 2; and Clough has a prima facie case for the relief claimed.

THE JURISDICTION POINT

26                  It is contended by Clough that this Court has jurisdiction in the proceedings.  In my view this is so because:  

(a)                Clough claims that ONGC has contravened and may again contravene s 51AA of the Act; 

(b)               by s 86(1) of the Act jurisdiction is conferred on this Court in any matter arising under the Actin respect of which a civil proceeding has been instituted under Part VI; and 

(c)                by s 39B(1A)(c) of the Judiciary Act 1903 (Cth), the original jurisdiction of this Court also includes jurisdiction in any matter arising under any laws made by the Commonwealth Parliament (other than criminal matters),

See generally: Traxon Industries Pty Ltd v Emerson Electric Co (2006) 230 ALR 297, 308 [50]-[51] ([2006] FCA 450).  See also, Burgundy Royale Investments v Westpac Banking Corporation (1987) 18 FCR 212, 219; Eurogold Ltd v Oxus Holdings (Malta) Ltd [2007] FCA 811 [15]-[19].

27                  Further, Clough’s other causes of action (namely for breach of contract) are sufficiently closely related to the cause of action based on unconscionable conduct that they form part of the same controversy and are, therefore, within the Court’s accrued jurisdiction: Traxon [52]; Eurogold [20].   

28                  I am satisfied, for the reasons which follow, that the proceeding is of a kind mentioned in several of the items contained within O 8, r 2. 

Item 3a

29                  Firstly, the proceeding arises in relation to contracts (namely, the performance guarantees) which were made in Australia and Clough seeks an order affecting these contracts: O 8, r 2, item 3.  Clough seeks injunctive relief to enjoin ONGC from serving demand under the performance guarantees.  This relief is claimed in futuro even though demand has already been made in respect of each of these.   

30                  Even though the performance guarantees are given in favour of ONGC by the banks, and even though Clough is a third party to the banks’ promise to pay, O 8, r 2, item 3 is in my opinion wide enough to cover Clough’s claim to enjoin conduct in relation to the performance guarantees: Tana v Baxter (1986) 160 CLR 572, 580, in relation to the similarly worded s 11(1)(b) of the old Service and Execution of Process Act 1901 (Cth). 

31                  Secondly, the proceeding arises in relation to the contract between Clough and ONGC, which contract was made in Australia and Clough seeks an order affecting that contract.  Even though the formal agreement was made on 6 January 2005 in India, the contract was made earlier on 30 November 2004 in Australia when ONGC sent its facsimile to Clough in Perth, where it was received instantaneously.  The facsimile expressly provided in para 8.0 that it constituted a binding contract between Clough and ONGC. Generally, instantaneous communications take effect at the place they are received: Entores Ltd v Miles Far East Corporation [1955] 2 QB 327, Sydbank Soenderjylland A/S v Bannerton Holdings Pty(1996) 68 FCR 539, 548-549. 

32                  Again, though the banks are not a party to the contract between Clough and ONGC, O 8, r 2, item 3 is wide enough to cover Clough’s claim to enjoin the banks from paying under to the performance guarantees because that is an order affecting the contract: Tana at 580. 

Item 11

33                  Further, the proceeding is based on a contravention of s 51AA of the Act that is committed (or threatened to be committed) in Australia: if ONGC wrongly threatened to call on the performance guarantees in the facsimiles of 29 January 2007 and 8 February 2007 (which were received in Perth) and wrongly served demand in Australia upon the Banks under the performance guarantees, ONGC, it is contended, has acted unconscionably in breach of s 51AA of the Act: Australian Competition and Consumer Commission v Samton Holdings Pty Ltd (2002) 117 FCR 301, 317; Boral Formwork v Action Makers (2003) ATPR 41-953, 47491-47494, Olex Focas Pty Ltd v Skodaexport Co Ltd [1998] 3 VR 380, 403-404.  I deal with the matter of unconscionable conduct below.

Item 12

34                  The proceeding is based on a breach of s 51AA of the Act (wherever occurring) seeking relief in relation to damage (financial and reputational) that will be suffered by Clough in Australia.  Clough will have to pay the banks in Australia and Clough will suffer financial damage and reputational damage in Australia if the performance guarantees are wrongly called.   

Item 21

35                 Finally, an injunction is sought in the proceeding ordering ONGC to refrain from taking any further steps in Australia calling on the performance guarantees or obtaining payment thereunder.  Injunctive relief that is ancillary to the causes of action based on breach of contract and unconscionability are within the court’s jurisdiction and may be granted to restrain conduct in Australia: Dunlop Rubber Co Ltd v Dunlop [1921] 1 AC 367, 371.  Under s 80(1) of the Act, the Court may grant an injunction to enjoin a person that has engaged or is proposing to engage in conduct that contravenes or would contravene s 51AA.  Under s 80(2) of the Act, the Court may grant an interim injunction if it considers that it is desirable to do so.

PRIMA FACIE CASE FOR THE RELIEF CLAIMED

36                  The threshold in this respect is not high.  In Western Australia v Vetter Trittler (1991) 30 FCR 102 at 110, French J expressed the opinion that a prima facie case is made out, if, on the material before the Court, inferences are open which if translated into findings of fact would support the relief claimed.  See also Merpro Montassa Ltd v Conoco Specialty Products Inc (1991) 28 FCR 387.   

37                  In my view, Clough has a prima facie case for the relief variously claimed in that, for reasons I set out below, ONGC would arguably be in breach of the contract and acting contrary to the express terms of the performance guarantees and acting unconscionably, in contravention of s 51AA of theAct, if it were to take further steps in making demands or obtaining payment under the performance guarantees: Merpro Montassa Ltd v Conoco Specialty Products Inc (1991) 28 FCR 387, 390; Western Australia v Vetter Trittler Pty Ltd (in liq) (1991) 30 FCR 102, 110; Sydbank Soenderjylland A/S v Bannerton Holdings Pty (1996) 68 FCR 539, 549; Eurogold Ltd v Oxus Holdings (Malta) Ltd [2006] FCA 1270. It is not necessary for an applicant seeking leave to show a prima facie cause of action in respect of each of the causes of action pleaded: Bray v F Hoffmann-La Roche Ltd (2003) 130 FCR 317; Traxon Industries Pty Ltd v Emerson Electric Co (2006) 230 ALR 297, 311 [65]. Nevertheless, Clough does so here.  

38                  Where I refer, in these reasons, to a claim, whether a construction point, or otherwise, being arguable, (or some derivative expression) I use it conveniently for present purposes to mean that it raises a serious issue to be tried but also that it represents a prima facie claim for the relief claimed. 

THE DISCRETION OF THE COURT

39                  Clough submits that this Court is not a clearly inappropriate forum: Voth v Manildra Flour Mills Pty Ltd (1990) 171 CLR 538, 570-571.  It points to the balance of factors weighing in favour of the competing jurisdiction:

(a)                The factors that favour an Indian court exercising jurisdiction include: ONGC is an Indian company; the project is in India and off the Indian coast; the proper law of the contract is Indian law and there is an exclusive jurisdiction clause, subject to the arbitration clause, in relation to the Courts of India.  

 

(b)               The factors that favour an Australian court exercising jurisdiction include: Clough is an Australian company; the parties could not have intended that the foreign jurisdiction/arbitration clause would apply to a TPA claim: Hi-Fert Pty Ltd v Kukiang Maritime Carrier Inc (1998) 90 FCR 1; it is the contractor to the project; importantly, the performance guarantees will be called in Australia and, in this proceeding, Clough seeks to enjoin the calling of the performance guarantees; and, if they are called, loss will be suffered by Clough in Australia. 


40                  There are other factors, however, which I consider, on balance, favour a view arguably that this Court is not a clearly inappropriate forum.  They are that:

(a)                Clough seeks urgent interlocutory relief (beyond the interim protection granted and to be granted) to enjoin the calling of performance guarantees and payment thereunder in Australia.  

(b)               In respect of its claim under the Act, Clough would be deprived of its right to seek to obtain declaratory and injunctive relief in respect of ONGC’s conduct said to contravene the Actif it were left to sue in India.

41                  The choice of the exclusive jurisdiction of the Courts of India in the Contract does not necessarily prevent this Court taking jurisdiction where there is a strong case for the Court doing so: Leigh-Mardon Pty Ltd v PRC Inc (1993) 44 FCR 88, 95-99. As I have mentioned, were the matter to be dealt with in India, Clough would be deprived of a legitimate personal or juridical advantage, namely its ability to invoke relief under the Act.  It is relevant, in this context to have regard to the object of the Actwhich, by s 2, is to enhance the welfare of Australians through the promotion of competition and fair trading and provision of consumer protection.  The remedy conferred by the Act, in respect to s 51AA cannot be lost, whatever the parties agree in their contract.  See, by analogy Clark Equipment Australia Ltd v Covcat Pty Ltd (1987) 71 ALR 367, 371.  The Act is ‘a public policy statute’.  Its operation cannot be ousted by private agreement. ‘Parliament passed the [TPA] to stamp out unfair or improper conduct in trade or in commerce; it would be contrary to public policy for special conditions such as those with which this contract was concerned to deny or prohibit a statutory remedy for offending conduct under the [TPA]’: Henjo Investments Pty Ltd v Collins Marrickville Pty Ltd (No 1) (1988) 39 FCR 546, 561.  See also IOOF Australia Trustees (NSW) Ltd v Tantipech (1998) 156 ALR 470, 478-480.  Any attempt to contract out of the remedies conferred by the Actmay be void: Hi-Fert Pty Ltd v Kukiang Maritime Carrier Inc (1998) 90 FCR 1, 24. 

42                  In Akai Pty Ltd v People Insurance Co Ltd (1996) 188 CLR 418, 445, the High Court confirmed that an application to stay proceedings on the basis that the proceedings were brought in breach of a foreign jurisdiction clause ‘may be refused where the foreign jurisdiction clause offends the public policy of the forum whether evinced by statute or declared by judicial decision’.  The policy of the Actmilitates against this Court refusing to accept jurisdiction.  The Court is required to give decisive weight to the effective operation of the Act: Akai, 447.   

43                  If an Australian protective provision would be avoided by forcing an applicant to sue in the courts of nominated jurisdiction, that is an important factor which should overcome the pre-disposition of the court to refuse to accept jurisdiction: Commonwealth Bank of Australia v White [1999] 2 VR 681, 704-705, [87]-[91]; Quinlan v Safe International Forsakrings AB [2005] FCA 1362, [49]; Hume Computers Pty Ltd v Exact International BV [2006] FCA 1440, [21]-[26]; see also [2006] FCA 1439, [35]. 

44                  The starting point is that the proper construction of the contract, the performance guarantees, and other contractual questions should be determined by applying the proper law of the contract: Permanent Trustee Co (Canberra) Ltd v Permanent Trustee Co of New South Wales Ltd (1969) 14 FLR 246, 254; L Collins, Dicey and Morris on The Conflict of Law (13th ed, 2000), [32-188].  The contract is governed by Indian law: cl 1.3.1.  As a general rule, there is a presumption that the law of a foreign country is the same as that of the forum, unless proven otherwise: Neilson v Overseas Projects Corp of Victoria Ltd (2005) 223 CLR 331, [116], [125], [249], [267].

45                  Clause 3.3 of the contract deals with the Performance Guarantee.  Arguably on its proper construction, its terms are as follows.

46                  Clough shall furnish an unconditional Performance Guarantee for the performance of the contract, in the form of Appendix III of Annexure A, for a sum equivalent to 10% of the contract price: cl 3.3.1.

47                  The Performance Guarantee is to be valid initially for the period to the original completion date of 30 April 2006, plus the 12 month Guarantee/Warranty period, plus 60 days: cl 3.3.1.

48                  If the works are delayed beyond the original completion date, whether the delay is attributable to ONCG, or to Clough, or for any other reasons (including force majeure), Clough shall extend the term of the Performance Guarantee so that it is valid for 12 months plus 60 days, from the actual date of completion of the works: cl 3.3.2.

49                  If the reason for delayed completion of the works is attributable to ONGC, then ONGC shall bear the cost of procuring the extension of the term of the Performance Guarantee: cl 3.3.2.

50                  Clough submits that ONGC only has the right to call on the Performance Guarantee where:

(a)                Clough acknowledges it is, or it is found following arbitral or other determination to be, in breach of contract, other than with respect to those provisions of the contract (cll 5.9.7.2 and 7.3.9) expressly giving ONGC the right to deduct moneys during the performance of the contract prior to practical completion;

(b)               Clough fails to pay moneys claimed by ONGC from Clough pursuant to cll 5.9.7.2 and 7.3.9;

(c)                Clough fails to pay for the cost of remedial works within 30 days during the Guarantee/Warranty period as required under cl 6.1.2;

(d)               ONGC has the right, once acknowledged by the contractor or established by arbitral or other determination, to recover liquidated damages under cl 6.3.2.

51                  This construction is said to emerge from consideration of the Contract read as a whole, especially cll 3.3.1, 3.3.3, 3.3.5, the reference to “breach” in Appendix III Annexure A.  If ONGC exercises its rights to call on the Performance Guarantee to recover liquidated damages, Clough shall cause the Performance Guarantee to be increased by the amount drawn down by the call, or cause a fresh Performance Guarantee to be given for that amount: cl 3.3.5.  I accept that, for present purposes, this construction is arguable. 

LIQUIDATED DAMAGES CLAIM

52                  Clough makes a number of submissions in this regard which I have set out below.

53                  A liquidated damages clause, included solely for the benefit of the principal (Company), is to be construed contra proferentum in the event of ambiguity: Peak Construction (Liverpool) Ltd v McKinney Foundations Ltd (1970)1 BLR 114 at 121; Darlington Futures Ltd v Delco Australia Pty Ltd (1986) 161 CLR 500 at 510.

54                  Where the parties have agreed liquidated damages for delay as a genuine pre-estimate of damage, rather than a penalty, the presumed intention of the parties is that absent express provisions to the contrary, the clause has no operation where the principal is a cause of the delay: Peak v McKinney at 121, 125-6, 127-8.

55                  A contrary intention may be shown where the parties have, in the terms of the contract itself, provided for a contractual mechanism for the determination of extensions of time where the principal is in default: Turner Corporation Ltd v Co-Ordinated Industries Pty Ltd (1995) 12 BCL 33.

56                  There is no provision in the contract by which the parties have expressly agreed to confer the power on a person (such as the Company’s Representative) to determine extensions of time (cf certification of Practical Completion and Discharge Certificate).

57                  Unless the parties have clearly expressed, in the wording of their contract, that a party or its agent is to be the sole and exclusive judge of what additional time should be allowed, such a construction should not be inferred, as it would put one party completely at the mercy of the other: Roberts v Bury Improvement Commissioners (1870) LR 5 CP 310 at 326-327, cited in Turner v Co-ordinated at 218. 

58                  The difficulty in inferring such a construction of the contract in this case is underscored when it is to be recalled that once the liquidated damages provisions properly apply, and the Performance Guarantee is called, the contractor is required to reinstate it in accordance with cl 3.3.5.  It could not have been intended that a mere assertion of an entitlement to liquidated damages would operate to allow the Company to recover the Performance Guarantee of up to US $21 million, and require the contractor to then re-instate that guaranteed amount, as continued security for the performance of the other contractual obligations of the contractor.

59                  Moreover, the parties in this matter have not expressly, or by necessary implication (e.g. by agreeing a new Construction Schedule with a new completion date) varied the contract to establish a new completion date in respect of which the liquidated damages clause may operate.

60                  Accordingly, in this case, where the Company has, by its breach, caused substantial delay to the off-shore works, the liquidated damages clause has no application.

61                  In my opinion, these submissions, upon the proper construction of the contract, are arguable.

PERFORMANCE GUARANTEES CANNOT BE CALLED IN BREACH OF CONTRACT

62                  Clough additionally makes the following submissions in this respect.

63                  There is clear authority for the propositions that:

(a)                a bank is required to pay on demand under an unconditional performance guarantee or bond (eg Edward Owen Engineering Ltd v Barclays Bank International Ltd [1978] 1 QB 159; Esal (Commodities) Ltd v Oriental Credit Ltd [1985] 2 Lloyd's Rep 546; IE Contractors Ltd v Lloyds Bank plc [1990] 2 Lloyd's Rep 496; Wood Hall Ltd v Pipeline Authority (1979) 141 CLR 443; Hortico (Aust) Pty Ltd v Energy Equipment Co (Aust) Pty Ltd [1985] 1 NSWLR 545); and 

(b)               a contractor cannot, therefore, obtain an injunction to restrain payment under an unconditional performance guarantee or bond without generally showing or pointing to fraud (eg Bolivinter Oil SA v Chase Manhattan Bank NA [1984] 1 WLR 392, 393; Themehelp Ltd v West [1996] QB 84; Solo Industries UK Ltd v Canara Bank [2001] 1 WLR 1800).

64                  However, it is always first a matter of construing the relevant performance guarantee to determine whether it does indeed create an unconditional or conditional obligation (eg conditional on showing breach by the contractor): Wood Hall Ltd v Pipeline Authority (1979) 141 CLR 443, 451 (Gibbs J), 459 (Stephen J); Pearson Bridge (NSW) Pty Ltd v State Rail Authority of New South Wales (1982) 1 Australian Construction LR 81; Selvas Pty Ltd v Hansen & Yuncken (SA) Pty Ltd (1987) 6 Australian Construction LR 36; Barclays Mowlem Construction Ltd v Simon Engineering (Australia) Pty Ltd (1991) 23 NSWLR 451, 456-457; Rejan Constructions Pty Ltd v Manningham Medical Centre Pty Ltd [2002] VSC 579, [4].

65                  If the entitlement to call on the performance guarantee is conditioned by the terms of the contract, it cannot be called unless the condition is met, and an injunction restraining an incorrect call may be obtained: eg Barclays Mowlem Construction Ltd v Simon Engineering (Australia) Pty Ltd (1991) 23 NSWLR 451, 456-457; Rejan Constructions Pty Ltd v Manningham Medical Centre Pty Ltd [2002] VSC 579, [4]; Anaconda Operations Pty Ltd v Fluor Daniel Pty Ltd [1999] VSCA 214, [8]; Bachmann Pty Ltd v BHP Power New Zealand Ltd [1999] 1 VR 420, [28]-[30]; Baulderstone Hornibrook Pty Ltd v Qantas Airways Ltd [2000] FCA 672, [10].

66                  As between the principal and the contractor, it is always relevant to determine whether the principal’s right to call on the performance guarantee or bond has actually arisen, and if it has not arisen, the principal may be restrained from incorrectly calling on the performance guarantee: Potton Holmes Ltd v Coleman Contractors Ltd (1984) 28 BLR 19, 28-29; Fletcher Construction Australia Ltd v Varnsdorf Pty Ltd [1998] 3 VR 812, 826.

67                  For example, as a matter of the proper construction of the contract between the principal and contractor, it may be that a performance guarantee is provided only as security for payments due under the contract, such that:

(a)                a principal is not entitled to make a call on the performance guarantee unless it is actually entitled to payment of an amount determined or agreed to be due: QS Retail Pty Ltd v Kingvest Pty Ltd [2006] VSC 455, [25], [33]-[34]; Fletcher Construction Australia Ltd v Varnsdorf Pty Ltd [1998] 3 VR 812; 

(b)               if it is called and paid, the money must be kept as security and not otherwise used: Rejan Constructions Pty Ltd v Manningham Medical Centre Pty Ltd [2002] VSC 579, [40].

68                  The many authorities in this area are no more than examples of the court’s construction of particular contracts in their particular context (Elian and Rabbath v Matsas [1966] 2 Lloyd’s Rep 495; Australian Winch and Haulage Company Pty Ltd (admin appt) v Walter Construction Group Ltd [2002] FCA 1181, [68]).  Suggestions that performance guarantees or bonds should be treated as ‘good as cash’ should not, therefore be regarded as conveying some proposition of general legal application.  The question remains, fundamentally, what was the intention of the parties, on the proper construction of the relevant contract.

69                  In this case as the conditions in cl 3.3 have not been satisfied, ONGC may not make a call under the performance guarantees, but having purported to do so, should be enjoined from taking any further steps to demand or obtain payment thereunder.

70                  Further, because Clough’s performance of the offshore work under the contract was and is conditional on ONGC’s performance of drilling and well-completion, ONGC’s failure to do that work without delay disqualifies ONGC from relying on any failure by Clough to complete the offshore work: Foran v Wight (1989) 168 CLR 385, 417, 425-426, 427 (Brennan J), 455 (Gaudron J); see also 442 (Dawson J); Newcombe v Newcombe (1934) 34 SR (NSW) 446, 450-451; Mackay v Dick (1881) 6 App Cas 251, 270. That again means that ONGC cannot purport to rely on Clough’s apparent delay, ignoring its own obligations under the contract, and thereby allege breach and seek to call on the performance guarantees.

71                  These matters are complex and of course the Court, in this ex parte application, obviously has not had the assistance of a proper contradictor.  Nonetheless, in my opinion, these matters are arguable although it has to be remembered that ONGC has already made calls under the performance guarantees.  It is also arguable that an injunction lies to restrain ONGC from taking further steps to demand or obtain payment, under the performance guarantees.  There remains the declaratory relief sought by Clough.  This raises the question of the asserted unconscionable conduct.

Unconscionable to call on performance guarantees

72                  Clough contends that it is unconscionable, in contravention of s 51AA of the Act, for ONGC to threaten to call, or to call, on the performance guarantees, when it is not entitled to do so.  It makes the following submissions. 

73                  Section 51AA provides that a corporation must not, in trade or commerce, engage in conduct that is unconscionable within the meaning of the unwritten law, from time to time, of the Australian State or Territories.

74                  ONGC is a ‘corporation’ for the purposes of s 51AA: s 4(1) of the Act.  It is a body corporate that is incorporated outside Australia within the meaning of Commonwealth Constitution s 51(xx).  It was incorporated in India under the Indian Companies Act 1956.

75                  By threatening to call the performance guarantees in correspondence received in Australia or by calling on the performance guarantees by serving notice on the banks in Australia, it has engaged in and will engage in conduct in trade or commerce.  By s 4(1) of the Act, ‘trade or commerce’ means trade or commerce within Australia or between Australia and places outside Australia. In Houghton v Arms (2006) 231 ALR 534, [33], the High Court accepted that in trade or commerce’ refers only to conduct having the character of being an aspect or element of trading or commercial activities or transactions.  ONGC’s conduct here qualifies as being part of its trading or commercial activities.

76                  The real issue is whether ONGC’s conduct is unconscionable within the meaning of the unwritten law.  There is authority that clearly supports the proposition that an inappropriate threat to call, or a call, on performance guarantees can be unconscionable conduct within s 51AA of the Act: see ACCC v Samton Holdings Pty Ltd (2002) 117 FCR 301, [46]-[50]. 

77                  In ACCC v CG Berbatis Holdings Pty Ltd (2003) 214 CLR 51, which was a case argued as case of advantage taking of a special disability (see [5], [45]-[46], [77], [160]-[161]), the High Court did not need to consider the point about whether s 51AA is confined to a only the case of advantage taking of a special disability or attracted a more general form of unconscionability. The point was expressly left undecided ([45]-[46], [77], [160]). In Tanwar v Enterprises Pty Ltd v Cauchi (2003) 217 CLR 315, [23]-26], although the High Court suggested that an element or hardship or unfairness alone might not be sufficient to enable the interference with contractual rights and that the phrase ‘unconscionable conduct’ was misleading, the High Court did not deal with the issue of the outer boundaries of s 51AA or the equitable doctrine of unconscionability.

78                  Further, equity has traditionally exercised its jurisdiction to curtail an exercise of a right to terminate if that right is sought to be used arbitrarily, or capriciously or unreasonably or in bad faith. Equity operates to prevent this conduct on the basis that it is unconscionable conduct: Pierce Bell Sales Pty Ltd v Frazer (1973) 130 CLR 575, 587; see also 587-588, 590-591; NC Seddon & MP Ellinghaus, Cheshire & Fifoot’s Law of Contract (8th Aust. ed) (2002), [20.9]. This doctrine, although distinct from, is very similar to, the implied contractual duty of good faith: Walker v ANZ Banking Group Ltd (No 2) (2001) 39 ACSR 557, [93]-[96], esp. [96].

79                  Because the issue as to the width of s 51AA has been left open and because equity has traditionally protected against unconscionable conduct, if there is an attempt to exercise a right unreasonably or in bad faith, it cannot be said that s 51AA does not extend to cover this sort of unconscionability. 

80                  I am satisfied that it is arguable that there has been an improper exercise of power by ONGC to take advantage of the banks’ propensity to pay, despite, again arguably, there being no right to call on the performance guarantees, amounting to unconscionable conduct by reference to:

(a)                equity’s traditional curtailment of a right to terminate if that right is exercised unreasonably or in bad faith; or 

(b)               the view in Samton that the court will treat as unconscionable a harsh or oppressive insistence on legal rights; or 

(c)                the view in Legione v Hateley (1983) 152 CLR 406 that a party, having caused or contributed to the other party’s breach, (delay in effecting a completion of the project) cannot now purport to exercise its rights: Olex Focas Pty Ltd v Skodaexport Co Ltd [1998] 3 VR 380; Boral Formwork v Action Makers (2003) ATPR 41-953. 

81                  It is, therefore arguably unconscionable, as Clough submits, that within the meaning of s 51AA of the Act, for ONGC to threaten to call, or to call, on the performance guarantees, to take advantage of the banks’ propensity to pay, despite, arguably, there being no right to call on the performance guarantees.  This is particularly so in circumstances where:

(a)                ONGC is itself in breach of the contract by failing to effect well-completion and by failing to pay some US $7 million;

(b)               the works are 83% complete and Clough has only been paid 65% of the original contract price;

(c)                Clough cannot complete the offshore work in the manner it was agreed; 

(d)               Clough has offered to do the shallow water work for extra cost but ONGC neither accepted this proposal nor directed that the shallow water work should be done in any event, and that the parties could resolve price later.

82                  By reason of the above matters, as I have said, it is at least arguable that ONGC is not entitled to call on the performance guarantees: Australian Broadcasting Corp v O'Neill (2006) 229 ALR 457, [65]-[71].

83                  Further, the balance of convenience favours the grant of an injunction because the evidence shows how Clough will be irreparably affected (both financially and through an adverse impact on its reputation) if ONGC presses its demands and secures payment under the performance guarantees. Damages would not be an adequate remedy for Clough, on the evidence. 

84                  Because the performance guarantees will remain intact or must be renewed (cl 3.3.6), ONGC will not suffer irreparable loss by the grant of an injunction. 

85                  In his affidavit sworn on 5 June 2007, Jae-Ho Choe has deposed that there is no convention treaty or other agreements in force between Australia and India on the service of documents in civil proceedings and further that the service of the Application and Affidavits, as proposed by means of a process server or legal practitioner in India, upon ONGC, is permitted by the law of India.  This satisfies the relevant provisions of FCR O 8 r 3(3). 

86                  Accordingly leave should be granted to serve the Amended Application outside of the jurisdiction and interim interlocutory injunctive relief should be afforded for a very short period.  I propose to make orders in terms of the Applicant’s Minute dated 6 June 2007.

 

I certify that the preceding eighty-six (86) numbered paragraphs are a true copy of the Reasons for Judgment herein of the Honourable Justice Gilmour .

 

Associate:

 

Dated:         7 June 2007


 

Counsel for the Applicant:

Mr G Murphy SC with Mr B Dharmananda

 

 

Solicitors for the Applicant:

Corrs Chambers Westgarth

 

 

Date of Hearing:

6 June 2007

 

 

Date of Judgment:

7 June 2007