FEDERAL COURT OF AUSTRALIA
Australian Competition and Consumer Commission v The Construction, Forestry, Mining and Energy Union [2006] FCA 1730
PROCEDURE – consent orders – whether within power of court to make – whether appropriate
Federal Court of Australia Act 1976 (Cth) s 21
Trade Practices Act 1974 (Cth) ss 45D, 76, 76(1), 80, 86C(1), 86C(2)(b), 86C(2)(c)
Federal Court Rules O 18 r 4
Ainsworth v Criminal Justice Commission (1992) 175 CLR 564
Australian Competition and Consumer Commission v Chen (2003) 132 FCR 309
Australian Competition and Consumer Commission v Goldy Motors (2000) 23 ATPR 41-801
Australian Competition and Consumer Commission v Humax Pty Ltd (2005) 27 ATPR
42-072
Australian Competition and Consumer Commission v On Clinic Australia Pty Ltd (1996) 18 ATPR 41-517
Australian Competition and Consumer Commission v Real Estate Institute of Western Australia (1999) 161 ALR 79
Australian Competition and Consumer Commission v Real Estate Institute of WA Inc (1999) 95 FCR 114
Australian Competition and Consumer Commission v Virgin Mobile Australia Pty Ltd (No 2) [2002] FCA 1548
Australian Competition and Consumer Commission v. Chaste Corporation Pty Ltd (in liq) [2005] FCA 1212
Australian Competition and Consumer Commission v. Midland Brick Co Pty Ltd (2004) 207 ALR 329
Thomson Australia Holdings Pty Ltd v Trade Practices Commission (1981) 148 CLR 150
Tobacco Institute of Australia Limited v Australian Federation of Consumer Organisations Inc (1993) 41 FCR 89
WAD 351 OF 2005
NICHOLSON J
12 DECEMBER 2006
PERTH
|
IN THE FEDERAL COURT OF AUSTRALIA |
|
|
WESTERN AUSTRALIA DISTRICT REGISTRY |
WAD 351 OF 2005 |
|
BETWEEN: |
AUSTRALIAN COMPETITION AND CONSUMER COMMISSION Applicant
|
|
AND: |
THE CONSTRUCTION, FORESTRY, MINING AND ENERGY UNION First Respondent
THE CONSTRUCTION, FORESTRY, MINING AND ENERGY UNION OF WORKERS Second Respondent
JOSEPH MCDONALD Third Respondent
MICHAEL BUCHAN Fourth Respondent
MICHAEL POWELL Fifth Respondent
|
|
NICHOLSON J |
|
|
DATE OF ORDER: |
12 DECEMBER 2006 |
|
WHERE MADE: |
PERTH |
BY CONSENT, THE COURT ORDERS THAT:
Declaration
CFMEU
Concrete Pour
1. A declaration that on 16 April 2004 the First Respondent (the “CFMEU”), by virtue of section 45DC of the Trade Practices Act 1974 (the “Act”), engaged in conduct at the construction site of a hotel called the ‘Holiday Inn’ situated adjacent to the premises of Burswood Casino in Burswood (the “Site”), a suburb of Perth in concert with the Third Respondent (“McDonald”) and the Fourth Respondent (“Buchan”) that hindered or prevented the supply of:
1.1 concrete from Readymix Holdings Pty Ltd (“Readymix”);
1.2 concrete pumping services from the business carried on by Graziano Tagni, Phillipa Tagni and Art West Pty Ltd under the business name Professional Concrete Pumping Services (the “PCPS Partnership”); and
1.3 concrete laying services from Unreel Structures Pty Ltd (known as “Unreel”),
to Doric Constructions (Australia) Pty Ltd (“Doric”), being conduct comprising of:
1.4 at approximately 6:45am, McDonald moving the chute of the Agitator containing concrete to face away from the PCPS concrete pumping machine;
1.5 McDonald and Buchan positioning themselves between the pumping machine and the Agitator; and
1.6 during the period from approximately 6:45am until approximately 7:03am McDonald and Buchan remaining positioned between the pumping machine and the Agitator,
which conduct was engaged in for the purpose, and would have or would be likely to have the effect of, causing substantial loss or damage to the business of Doric, in contravention of section 45D(1) of the Act.
Union Line
2.1 concrete from Readymix;
2.2 concrete pumping services from the PCPS Partnership; and
2.3 concrete laying services from Unreel,
to Doric, being conduct comprising of:
2.4 McDonald and Buchan instructing other persons to form a physical barrier between a Readymix concrete agitator and the Entrance Gate; and
2.5 McDonald and Buchan and those other persons participating in the Union Line,
which conduct was engaged in for the purpose, and would have or would be likely to have the effect of, causing substantial loss or damage to the business of Doric, in contravention of section 45D(1) of the Act.
Physical Barrier and November Union Line
3. A declaration that on 4 November 2004 the CFMEU, by virtue of section 45DC of the Act, engaged in conduct at the Site in concert with McDonald and the Fifth Respondent (“Powell”) that hindered or prevented the supply of goods or services from WA Bins Pty Ltd (“WA Bins”), namely the delivery of sand, to Doric, being conduct comprising of McDonald and Powell and other persons forming a physical barrier between the front of a truck from WA Bins (the “WA Bins Truck”) and the Entrance Gate to the Site (the “Physical Barrier”) which conduct was engaged in for the purpose, and would have or would be likely to have the effect of, causing substantial loss or damage to the business of Doric, in contravention of section 45D(1) of the Act.
CFMEUW
Concrete Pour
4. A declaration that on 16 April 2004 the Second Respondent (the “CFMEUW”), by virtue of section 45DC of the Act, engaged in conduct at the Site in concert with McDonald and Buchan that hindered or prevented the supply of:
4.1 concrete from Readymix;
4.2 concrete pumping services from the PCPS Partnership; and
4.3 concrete laying services from Unreel,
to Doric, being conduct comprising of:
4.4 at approximately 6:45am, McDonald moving the chute of the Agitator containing concrete to face away from the PCPS concrete pumping machine;
4.5 McDonald and Buchan positioning themselves between the pumping machine and the Agitator; and
4.6 during the period from approximately 6:45am until approximately 7:03am McDonald and Buchan remaining positioned between the pumping machine and the Agitator;
which conduct was engaged in for the purpose, and would have or would be likely to have the effect of, causing substantial loss or damage to the business of Doric, in contravention of section 45D(1) of the Act.
Union Line
5. A declaration that on 16 April 2004 the CFMEUW, by virtue of section 45DC of the Act, engaged in conduct at the Site in concert with McDonald and Buchan that hindered or prevented the supply of:
5.1 concrete from Readymix;
5.2 concrete pumping services from the PCPS Partnership; and
5.3 concrete laying services from Unreel,
to Doric, being conduct comprising of:
5.4 McDonald and Buchan instructing other persons to form a physical barrier between a Readymix concrete agitator and the Entrance Gate; and
5.5 McDonald and Buchan and those other persons participating in the Union Line,
which conduct was engaged in for the purpose, and would have or would be likely to have the effect of, causing substantial loss or damage to the business of Doric, in contravention of section 45D(1) of the Act.
Physical Barrier and November Union Line
6. A declaration that on 4 November 2004 the CFMEUW, by virtue of section 45DC of the Act, engaged in conduct at the Site in concert with McDonald and Powell that hindered or prevented the supply of goods or services from WA Bins, namely the delivery of sand, to Doric, being conduct comprising of McDonald and Powell and other persons forming the Physical Barrier which conduct was engaged in for the purpose, and would have or would be likely to have the effect of, causing substantial loss or damage to the business of Doric, in contravention of section 45D(1) of the Act.
McDonald
Concrete Pour
7. A declaration that on 16 April 2004 McDonald engaged in conduct at the Site in concert with Buchan that hindered or prevented the supply of:
7.1 concrete from Readymix;
7.2 concrete pumping services from the PCPS Partnership; and
7.3 concrete laying services from Unreel,
to Doric, being conduct comprising of:
7.4 at approximately 6:45am, McDonald moving the chute of the Agitator containing concrete to face away from the PCPS concrete pumping machine;
7.5 McDonald and Buchan positioning themselves between the pumping machine and the Agitator; and
7.6 during the period from approximately 6:45am until approximately 7:00am McDonald and Buchan remaining positioned between the pumping machine and the Agitator,
which conduct was engaged in for the purpose, and would have or would be likely to have the effect of, causing substantial loss or damage to the business of Doric, in contravention of section 45D(1) of the Act.
Union Line
8. A declaration that on 16 April 2004 McDonald engaged in conduct at the Site in concert with Buchan that hindered or prevented the supply of:
8.1 concrete from Readymix;
8.2 concrete pumping services from the PCPS Partnership; and
8.3 concrete laying services from Unreel,
to Doric, being conduct comprising of:
8.4 McDonald and Buchan instructing other persons to form a physical barrier between a Readymix concrete agitator and the Entrance Gate; and
8.5 McDonald and Buchan and those other persons participating in the Union Line,
which conduct was engaged in for the purpose, and would have or would be likely to have the effect of, causing substantial loss or damage to the business of Doric, in contravention of section 45D(1) of the Act.
Physical Barrier and November Union Line
9. A declaration that on 4 November 2004 McDonald engaged in conduct at the Site in concert with Powell that hindered or prevented the supply of goods or services from WA Bins, namely the delivery of sand, to Doric, being conduct comprising of McDonald and Powell and other persons forming the Physical Barrier which conduct was engaged in for the purpose, and would have or would be likely to have the effect of, causing substantial loss or damage to the business of Doric, in contravention of section 45D(1) of the Act.
Buchan
Concrete Pour
10. A declaration that on 16 April 2004 Buchan engaged in conduct at the Site in concert with McDonald that hindered or prevented the supply of:
10.1 concrete from Readymix;
10.2concrete pumping services from the PCPS Partnership; and
10.3concrete laying services from Unreel,
to Doric, being conduct comprising of:
10.4at approximately 6:45am, McDonald moving the chute of the Agitator containing concrete to face away from the PCPS concrete pumping machine;
10.5McDonald and Buchan positioning themselves between the pumping machine and the Agitator; and
10.6during the period from approximately 6:45am until approximately 7:00am McDonald and Buchan remaining positioned between the pumping machine and the Agitator,
which conduct was engaged in for the purpose, and would have or would be likely to have the effect of, causing substantial loss or damage to the business of Doric, in contravention of section 45D(1) of the Act.
Union Line
11. A declaration that on 16 April 2004 Buchan engaged in conduct at the Site in concert with McDonald that hindered or prevented the supply of:
11.1 concrete from Readymix;
11.2concrete pumping services from the PCPS Partnership; and
11.3concrete laying services from Unreel,
to Doric, being conduct comprising of:
11.4McDonald and Buchan instructing other persons to form a physical barrier between a Readymix concrete agitator and the Entrance Gate; and
11.5McDonald and Buchan and those other persons participating in the Union Line,
which conduct was engaged in for the purpose, and would have or would be likely to have the effect of, causing substantial loss or damage to the business of Doric, in contravention of section 45D(1) of the Act.
Powell
12. A declaration that on 4 November 2004 Powell engaged in conduct at the Site in concert with McDonald that hindered or prevented the supply of goods or services from WA Bins, namely the delivery of sand, to Doric, being conduct comprising of McDonald and Powell and other persons forming the Physical Barrier which conduct was engaged in for the purpose, and would have or would be likely to have the effect of, causing substantial loss or damage to the business of Doric, in contravention of section 45D(1) of the Act.
Trade Practices Compliance Program
13. An order directing that each of the First and Second Respondents:
13.1 within three months of the date of this order, establish an education training and trade practices compliance program (“the Compliance Program”) for officers, employees, agents or other persons involved in the First or Second Respondents’ activities:
13.1.1 who are employed, or engage in conduct in Western Australia; and
13.1.2 whose duties might conceivably give rise to the risk of relevant contraventions of the Act,
which is designed to ensure:
13.1.3 an awareness of the responsibilities and obligations contained in sections 45D to 45EB of the Act and of the responsibilities and obligations in relation to the contravening conduct in this proceeding or any similar or related conduct; and
13.1.4 subject to the Compliance Program being tailored to the respective Respondent’s circumstances, it be consistent with the Australian Standard on Compliance Programs AS3806;
13.2within one month of the date of this order appoint a person with experience in trade practices law to advise the respective Respondents as to the content of the Compliance Program;
13.3implement and administer the Compliance Program for a period of 3 years from the date it is established; and
13.4within three months of the date of this order provide a written report to the Applicant on the content of the Compliance Program and provide a further report to the Applicant on the implementation and administration of the Compliance Program at the conclusion of each period of 12 months during which the program is being implemented and administered.
Disclosure Orders
14. An order that each of the First and Second Respondents publish to each of their officers, employees, agents and members a notice in the form of Annexure A within 30 days of the date of this order.
Pecuniary Penalties
15. An order that the First Respondent pay to the Commonwealth of Australia a pecuniary penalty in the amount of $50,000.00 pursuant to section 76(1) of the Act in respect of the contraventions of section 45D of the Act by the First Respondent alleged in the Statement of Claim filed herein within 28 days of the making of this order.
16. An order that the Second Respondent pay to the Commonwealth of Australia a pecuniary penalty in the amount of $50,000.00 pursuant to section 76(1) of the Act in respect of the contraventions of section 45D of the Act by the Second Respondent alleged in the Statement of Claim filed herein within 28 days of the making of this order.
Other Orders
17. The First and Second Respondents pay the Applicant’s costs agreed and fixed at $15,000.00 in total within 28 days of the making of this order.
Note: Settlement and entry of orders is dealt with in Order 36 of the Federal Court Rules.
|
IN THE FEDERAL COURT OF AUSTRALIA |
|
|
WESTERN AUSTRALIA DISTRICT REGISTRY |
WAD 351 OF 2005 |
|
BETWEEN: |
AUSTRALIAN COMPETITION AND CONSUMER COMMISSION Applicant
|
|
AND: |
THE CONSTRUCTION, FORESTRY, MINING AND ENERGY UNION First Respondent
THE CONSTRUCTION, FORESTRY, MINING AND ENERGY UNION OF WORKERS Second Respondent
JOSEPH MCDONALD Third Respondent
MICHAEL BUCHAN Fourth Respondent
MICHAEL POWELL Fifth Respondent
|
|
JUDGE: |
NICHOLSON J |
|
DATE: |
12 DECEMBER 2006 |
|
PLACE: |
PERTH |
REASONS FOR JUDGMENT
1 The applicant (the Commission) seeks orders against the respondents. Pursuant to an agreement between the parties, the Commission and the respondents have filed a minute of proposed final consent orders dated 1 December 2006 (Minute of Consent Orders). Pursuant to the same agreement between the parties they have also filed joint submissions and an agreed statement of facts. Each of the respondents have also filed a further amended defence in which they each admit the allegations of contraventions of s 45D of the Trade Practices Act 1974 (Cth) (the Act). The effect of the admissions is to trigger the application of O 18 r 4 of the Federal Court Rules (FCR) which provides:
‘4(1) If an admission is made by a party, whether by a pleading or otherwise, the Court may pronounce any judgment or make any order to which the applicant is entitled on the admission.
4(2) The Court may exercise its powers under sub-rule (1) notwithstanding that other questions in the proceeding have not been determined.’
2 The nature of the proceeding is as follows. It concerns conduct which occurred at the construction site of the ‘Holiday Inn’ situated adjacent to the premises of Burswood Casino in Burswood, Western Australia on 16 April 2004 and 4 November 2004. The claims of the Commission are, and the respondents each admit, that they engaged in certain conduct in contravention of s 45D of the Act. That conduct is described as follows in the joint submissions:
‘1.1 the “Concrete Pour Incident” on 16 April 2004 the facts concerning which are agreed and referred to in paragraphs 10-29 of the Statement of Agreed Facts. The Concrete Pour Incident involved the Union Respondents, McDonald and Buchan. On 16 April 2004:
1.1.1 Doric had scheduled a concrete pour for the central lift well of the Holiday Inn. The central lift well was a critical component of the construction of the Holiday Inn. Readymix was engaged to deliver 120 cubic metres of pre-mixed concrete over the course of the day via a number of concrete agitators attached to the back of trucks (“Agitators”). The concrete was to be discharged from the Agitators via a chute into a concrete pumping machine operated by the PCPS Partnership. The PCPS Partnership was then to pump the concrete into the pour area where Unreel would lay and flush the concrete;
1.1.2 during the period from approximately 6:45am until 7:03am McDonald and Buchan together stood between a Readymix Agitator and the PCPS Partnership concrete pumping machine, thereby hindering or preventing:
1.1.2.1 Readymix from supplying concrete to Doric as scheduled;
1.1.2.2 PCPS Partnership from supplying concrete pumping services to Doric as scheduled; and
1.1.2.3 Unreel from supplying concrete laying services to Doric as scheduled; and
1.1.3 the conduct was engaged in for the purpose of causing substantial loss or damage to the business of Doric; and
1.1.4 the conduct would have, or would be likely to have, the effect of causing substantial loss or damage to the business of Doric;
1.2 the “Union Line Incident” on 16 April 2004 the facts concerning which are agreed and referred to in paragraphs 30-42 of the Statement of Agreed Facts. The Union Line Incident involved the Union Respondents, McDonald and Buchan. On 16 April 2004 after McDonald and Buchan were escorted from the Site by the Western Australian Police following the Concrete Pour Incident:
1.2.1 from 7:03am until 7:34am, McDonald and Buchan were joined by a number of other persons (the “Group”), one or more of whom were members of the Union Respondents (the “Union Members”) in the area outside the entrance gate to the Site (the “Entrance Gate”);
1.2.2 at 7:34am, a fourth Agitator from Readymix arrived at the Site and attempted to enter the Site in order to deliver concrete. This was followed by the arrival of three further Agitators at the Site;
1.2.3 from 7:34am, McDonald, Buchan and members of the Group, including one or more Union Members, formed a physical barrier by standing in a line across the Entrance Gate (the “Union Line”), preventing the Agitators from entering the Site, resulting in the cancellation of the concrete pour and thereby hindering or preventing:
1.2.3.1 Readymix from supplying concrete to Doric;
1.2.3.2 PCPS Partnership from supplying concrete pumping services to Doric; and
1.2.3.3 Unreel from supplying concrete laying services to Doric; and
1.2.4 the conduct was engaged in for the purpose of causing substantial loss or damage to the business of Doric; and
1.2.5 the conduct would have, or would be likely to have, the effect of causing substantial loss or damage to the business of Doric; and
1.3 the “November Union Line Incident” on 4 November 2004 the facts concerning which are agreed and referred to in paragraphs 43-57 of the Statement of Agreed Facts. The November Union Line Incident involved the Union Respondents, McDonald and Powell. On 4 November 2004:
1.3.1 from approximately 5:15am, the Union Respondents, McDonald, Powell and a number of other persons (“the November Group”), one or more of whom were members and/or officers of the Union Respondents (the “November Union Members”), were present in the area outside the Entrance Gate;
1.3.2 at approximately 10:47am, a truck from WA Bins carrying two bins of sand arrived at the Entrance Gate;
1.3.3 McDonald, Powell and members of the November Group, including one or more November Union Members, created a physical barrier between the front of the WA Bins truck and the Entrance Gate (the “Physical Barrier”) and later stood in lines across the Entrance Gate (the “November Union Line”) preventing the WA Bins truck from entering the Site and thereby hindering or preventing WA Bins from supplying sand to Doric;
1.3.4 the conduct was engaged in for the purpose of causing substantial loss or damage to the business of Doric; and
1.3.5 the conduct would have, or would be likely to have, the effect of causing substantial loss or damage to the business of Doric.’
3 The Commission recognises that, notwithstanding the agreement reached between the parties as to the terms of the proposed consent orders, it is for the Court to determine whether or not it has the power to make the orders proposed, and whether, in all the circumstances it is appropriate to do so. The Court must not exceed its power in the making of consent orders. The parties cannot by consent confer power to the Court to make orders which the Court lacks the power to make: Thomson Australia Holdings Pty Ltd v Trade Practices Commission (1981) 148 CLR 150 at 165 and followed by French J in Australian Competition and Consumer Commission v Real Estate Institute of Western Australia (1999) 161 ALR 79 at [19] (ACCC v REIWA 161 ALR).
4 In considering proposed consent orders the Court should not impede settlements between parties legally represented and able to understand and evaluate the desirability of agreeing to that settlement. It should not refuse to give effect to the terms of settlement by refusing to make orders or accept undertakings where they are within the Court’s jurisdiction and are otherwise unobjectionable. Nor should it simply substitute its own view of the orders or undertakings which it would have made if those proffered fall within the range of an appropriate disposition of the case: ACCC v REIWA 161 ALR at [22] and Australian Competition and Consumer Commission v Virgin Mobile Australia Pty Ltd (No 2) [2002] FCA 1548 at [2] (Virgin Mobile (No 2) FCA 1548).
5 The remedies which are sought by consent are as follows:
1. declarations against each of the respondents as to the unlawfulness of the conduct as provided in the Minute of Consent Orders;
2. disclosure orders against the first and second respondents pursuant to ss 86C(1) and 86C(2)(c) of the Act as provided in the Minute of Consent Orders;
3. orders requiring the first and second respondents to implement a corporate compliance program pursuant to ss 80, 86C(1) and 86C(2)(b) of the Act as provided in the Minute of Consent Orders;
4. an order that the first respondent pay a pecuniary penalty to the Commonwealth of Australia in the amount of $50 000 pursuant to s 76 of the Act as provided in the Minute of Consent Orders;
5. an order that the second respondent pay a pecuniary penalty to the Commonwealth of Australia in the amount of $50 000 pursuant to s 76 of the Act as provided in the Minute of Consent Orders; and
6. an order that the respondents pay the Commission’s costs of these proceedings fixed at $15 000 as provided in the Minute of Consent Orders.
6 So far as concerns the declarations against each of the respondents proposed in the Minute of Consent Orders, I consider they are within s 21 of the Federal Court of Australia Act 1976 (Cth) and appropriate for the following reasons. They:
1. are an appropriate vehicle to record the Court’s disapproval of the contravening conduct (Tobacco Institute of Australia Limited v Australian Federation of Consumer Organisations Inc (1993) 41 FCR 89 at 100; Australian Competition and Consumer Commission v Chen (2003) 132 FCR 309 at [36] (Chen 132 FCR));
2. serve to vindicate the Commission’s claim that the respondents contravened the Act (Australian Competition and Consumer Commission v Goldy Motors (2000) 23 ATPR 41-801 at [34] (Goldy Motors 23 ATPR));
3. are of some assistance to the Commission in the future in carrying out the duties which are conferred upon it by the Act (Goldy Motors 23 ATPR at [34]);
4. are of assistance in clarifying the law (Goldy Motors 23 ATPR at [34]; Australian Competition and Consumer Commission v. Chaste Corporation Pty Ltd (in liq) [2005] FCA 1212 at [146]);
5. may inform consumers of the dangers arising from a respondent’s contravening conduct (Chen 132 FCR at [48]); and
6. may deter corporations from contravening the Act (Australian Competition and Consumer Commission v. Midland Brick Co Pty Ltd (2004) 207 ALR 329 at [22]).
7 As to the appropriateness of the declaratory relief, they are directed to the determination of legal controversies and not to answering abstract or hypothetical questions: Ainsworth v Criminal Justice Commission (1992) 175 CLR 564 at 582 per Mason CJ, Dawson, Toohey and Gaudron JJ. Here the matters in issue have been identified and particularised and admitted by the respondents. The Commission, as a public body charged with enforcing the Act, has a real interest in seeking the relief (Goldy Motors 23 ATPR at [30]), and the respondents are in the position of a proper contradictor (in that they have a true interest in opposing the declarations sought).
8 As to the disclosure orders, I accept these are authorised by s 86C(2)(c) of the Act read together with s 86C(1). The section is not intended to be punitive. Rather, its purpose is to protect the public interest by dispelling any incorrect impressions that arise from misleading representations and raising public awareness about the type of conduct that may contravene the Act: Australian Competition and Consumer Commission v On Clinic Australia Pty Ltd (1996) 18 ATPR 41-517; Australian Competition and Consumer Commission v Real Estate Institute of WA Inc (1999) 95 FCR 114.
9 The orders directed to a compliance program are authorised by the sections referred to in the Minute of Consent Orders.
10 In Virgin Mobile (No 2) FCA 1548, French J at [24] considered the application of s 86C with respect to compliance programs and took the view that orders for trade practices compliance programs should be expressed with sufficient precision to enable a breach of the order to be readily ascertained and effectively punished. However, as contemplated by s 86C, in making such orders for compliance programs it may be that it is neither practicable nor useful to prescribe with minute particularity the content of such programs.
11 The program proposed in the Minute of Consent Orders requires that the compliance program be implemented for the officers, employees, agents and other persons involved in the union respondents’ relevant activities, in order to ensure that they are aware of their responsibilities and obligations in relation to ss 45D to 45EB of the Act and minimise risk of future breaches of those provisions.
12 In Australian Competition and Consumer Commission v Humax Pty Ltd (2005) 27 ATPR 42-072, Merkel J made an order for a compliance program in substantively the same terms as the program proposed in the Minute of Consent Orders. His Honour observed at [15] that the compliance program ‘is an order that is "for the purpose of ensuring that the [contravening party] does not engage in the contravening conduct, similar conduct or related conduct" and is therefore authorised by s 86C of the Act’.
13 The orders imposing pecuniary penalties find their authority in s 76(1) of the Act. The Court may impose a pecuniary penalty of up to $750 000 for each act or omission by each of the Union respondents that is found to contravene s 45D of the Act (s 76(1A)). The Court may not impose a pecuniary penalty on an individual for a contravention of s 45D (s 76(2)).
14 In the joint submissions attention is drawn to the following factors relevant to the fixing of the quantum of the pecuniary penalties. It is accepted that the first and second respondents have cooperated with the Commission by approaching the Court for the final disposition of the proceedings on a non-contested basis. It is accepted also that those respondents did not engage in the conduct for their own financial gain or the financial gain of their officials. In relation to deterrence it is accepted that there are two aspects to it, namely, specific deterrence and general deterrence. The submissions accept that regard must be had to the totality principle and the parity principle.
15 In my opinion the pecuniary penalties proposed in the Minute of Consent Orders properly have regard to the range of circumstances arising pursuant to s 76 of the Act which are more extensively developed in the joint submissions.
16 The power to award costs arises under s 43(1) of the Act. There is no reason not to give effect to the agreement reached in that regard.
17 In forming these views I have relied upon the joint submissions, in particular, and the admissions made by the respondents.
18 Therefore I consider that the Minute of Consent Orders should be accepted. Accordingly, on the publication of these reasons, I will sign that Minute pursuant to FCR O 35 r 10 directing the District Registrar to draw up, sign and seal an order in accordance with the terms of the Minute of Consent Orders.
|
I certify that the preceding eighteen (18) numbered paragraphs are a true copy of the Reasons for Judgment herein of the Honourable Justice Nicholson J. |
Associate:
Dated: 12 December 2006
|
Counsel for the Applicant: |
N Owen-Conway |
|
|
|
|
Solicitor for the Applicant: |
Australian Government Solicitor |
|
|
|
|
Counsel for the Respondents: |
D Guidolin |
|
|
|
|
Solicitor for the Respondents: |
Slater &Gordon Lawyers |
|
|
|
|
Date of Hearing: |
1 December 2006 |
|
|
|
|
Date of Judgment: |
12 December 2006 |